Dorsten/Wulfen (ABZ)
The process of rehabilitating underground service connections is an innovative service offered by Kettler GmbH. Thanks to this Dorsten-based company, utility providers can restore defective or damaged service connections to operational condition directly through the manhole cover.
Compared to existing methods for repairing or refurbishing built-in fixtures, this process differs in four key areas:
Only a minor incision is required directly through the manhole cover, so there is no damage to the road and no open hole. In addition, the method is considered quick and clean.
A manhole assembly rehabilitation is a minimally invasive procedure performed directly through the manhole cover. In this process, defective manhole assemblies are restored to working order or replaced with new ones.
Vacuuming creates an annular space extending to the top of the fixture. Next, an assessment of the current condition of the connection between the installation kit and the fixture is performed. Depending on its condition, the defective installation kit is either repaired or completely replaced. Finally, the annular space is filled with a special liquid sealant.
This method is used in underground pipeline construction for installation kits mounted on heavy-duty fittings. The manhole cover should have an internal diameter of at least 100 mm. This allows for the installation and removal of components, as well as their proper assembly, later on. The average duration of a rehabilitation project is approximately 2.5 hours.
Source Allgemeine Bauzeitung, Issue 37, September 15, 2017